The Product Owner complains to you that the team is not working hard enough and they need to increase their velocity by at least 50%. Which action should you not take?

Advertisement

  • Share the feedback from the PO and challenge the team to increase their velocity.
  • Ask the PO to explain the business context to the team.
  • Explain the impact of technical debt to the PO and the benefits of devoting some capacity to reducing it.
  • Hold a Value Stream Mapping workshop to identify and reduce waste.