What is the Product Owner’s role in deciding the priority of work in the sprint backlog?

Advertisement

  • None—the Scrum Master should prioritize the work in the sprint backlog.
  • The PO should prioritize the items in the sprint backlog.
  • The developers prioritize work unless they cannot complete it, in which case the PO should prioritize the remaining work.
  • None—the developers should prioritize the work in the sprint backlog.